BIM Services for Data Center
Coordinated, construction-ready models for mission-critical facilities, from white space to central plant.
One model that power, cooling, IT and construction teams can all build from.
One model that power, cooling, IT and construction teams can all build from. Data centers pack more services into less space than almost any other building type. Busways, chilled water mains, CRAH units, fire suppression, cable trays and containment all compete for the same few hundred millimetres above the racks. A single clash found on site can delay commissioning by weeks and push back the date the first rack goes live.
Our BIM team builds detailed, coordinated models of your facility before construction starts. We model architecture, structure and every MEP system to the level of detail your project needs, run clash detection across all trades, and turn the agreed model into shop drawings, prefabrication spools and quantity take-offs.
We work on hyperscale campuses, colocation facilities, enterprise data halls and modular edge sites, both new builds and live-site retrofits. Teams join at concept, design development or pre-construction, and we can hand over an asset-ready model for facility operations once the building is complete.
Data Centers We Model
Every facility type has different constraints. We plan for each one.
Hyperscale Campuses
Multi-building sites with repeatable halls, where model standards and prefab speed matter most.
Colocation Facilities
Flexible white space, cages and suites built in phases as tenants move in.
Enterprise Data Halls
In-house server rooms and data halls inside offices, hospitals, banks and campuses.
Modular & Edge Sites
Containerised and prefabricated units, modeled for factory build and fast site assembly.
AI & High-Density Halls
High rack densities with direct-to-chip or immersion liquid cooling and heavier power loads.
Retrofits & Expansions
Upgrades inside live facilities, planned around equipment that must stay running.
Our Approach
A clear, four-stage process from first drawings to handover.
Scope & BIM Execution Plan
Federated models checked in Navisworks for hard and soft clashes, with weekly clash reports and coordination meetings until every trade signs off.
Modeling by Discipline
Architecture, structure, electrical, mechanical, plumbing and fire protection are modeled in parallel, each to the agreed level of detail.
Coordination & Clash Resolution
Models are federated and checked for clashes. We resolve issues with your engineers and contractors until every system fits and can be maintained.
Deliverables & Handover
You receive coordinated models, shop drawings, take-offs and, if required, a COBie-ready model for facility management and operations.
What a coordinated model changes on a data center project.
Faster time to go-live
Less rework and waste
Ready for prefabrication
Built for uptime
Easier future expansion
Deliverables & Level of Development
Choose the detail level that matches your project stage.
| LOD | Best for | What you receive |
|---|---|---|
| LOD 200 | Concept and feasibility | Massing models, space planning and early capacity studies |
| LOD 300 | Design development | Accurate sizes and locations of all systems, design coordination, 2D drawings |
| LOD 350 | Pre-construction | Supports, hangers and connections between systems, clash-free coordinated models |
| LOD 400 | Fabrication and installation | Shop drawings, spool drawings, prefabrication models and quantity take-offs |
| LOD 500 | Handover and operations | Field-verified as-built model with asset data (COBie) for facility management |
Autodesk Revit
Navisworks Manage
AutoCAD MEP
BIM 360 / ACC
Recap Pro
Dynamo
Synchro 4D
Coordinated BIM for a 24 MW Tier III colocation data center
We delivered LOD 400 models of every discipline, full MEP coordination and prefabrication drawings for a two-storey colocation facility built on a fast-track programme.
Global colocation provider
Frankfurt, Germany
18,500 m² / 24 MW IT load
4 halls, 1,600 racks
Arch, Structure, MEP, FP — LOD 400
Revit, Navisworks, ACC
Tier III, N+1 cooling, 2N power
7 months
The challenge
The client needed the first two data halls live in 14 months. Design was still changing when construction started, and five trade contractors were working from separate 2D drawings. The ceiling void above the white space had to fit busways, cable trays, chilled water mains, fire suppression and containment in under 1.2 metres, with clear maintenance access for every critical component.
Our solution
We set up a BIM Execution Plan in the first week and built a federated model of architecture, structure and all MEP systems. Weekly clash detection in Navisworks, with tracked issues and assigned owners, let each trade see and fix problems before they reached site.
Once routes were agreed, we produced LOD 400 shop drawings, pipe spool drawings and electrical skid layouts so the contractor could prefabricate off site. 4D sequencing linked to the model helped plan a phased build, so Halls 1 and 2 could open while Halls 3 and 4 were still under construction.
The outcome
The model was clash-free before installation began in the data halls. Prefabricated assemblies went in faster with almost no site modification, and the client received a COBie-ready as-built model for facility operations at handover.
Our BIM Services
Full-scope modeling and coordination for every system in a data center.
Architectural & Structural Modeling
Data halls, raised floors, plinths, roof plant areas and structural framing modeled to LOD 300–400, including load-bearing zones for heavy equipment.
Electrical & Power Distribution
Utility intake, generators, UPS, switchgear, busways, PDUs, RPPs and cable tray routing, with clearances and maintenance access built in.
Mechanical & Cooling Systems
Chillers, CRAH/CRAC units, chilled water piping, in-row and liquid cooling loops, and hot/cold aisle containment, ready for CFD analysis.
White Space & Rack Layout
Rack, cabinet and cage layouts with structured cabling, fibre pathways and overhead or underfloor distribution, coordinated with power and cooling.
MEP Coordination & Clash Detection
Federated models checked in Navisworks for hard and soft clashes, with weekly clash reports and coordination meetings until every trade signs off.
Shop Drawings & Prefabrication
Fabrication-level LOD 400 models, spool drawings and skid layouts for off-site manufacture of piping, electrical racks and modular units.
4D Scheduling & 5D Cost
Construction sequences linked to the model to plan phased build-outs, plus quantity take-offs for accurate cost estimates and procurement.
Scan to BIM & As-Built Models
Laser scan point clouds turned into accurate as-built models of existing facilities, for retrofits, capacity upgrades and live-site expansions.
A BIM partner that understands mission-critical work
Data centers leave no room for error. Our team plans every route, clearance and connection so your facility is built right the first time.
Data center specialists
All trades in one model
Fast turnaround
Standards you can trust
Secure and confidential
One point of contact
Scanned Projects Delivered
Years of BIM Experience
Qualified BIM Professionals
Client Satisfaction Rate
What Project Teams Say About Working With Us
Honest words from the people behind our continued success
Popular Questions
Answers to common questions about BIM for data center projects.
What types of data center projects do you support?
Which level of development (LOD) do I need?
Can you model an existing data center while it is operating?
What inputs do you need to get started?
How do you share models and track clashes?
Planning a new data center or an upgrade?
Send us your drawings and we will show you how a coordinated BIM model can protect your schedule.